Steps to Building A Car Wash
The following is a list of the typical steps you will follow when building a car wash.
1. Estimate the cost of construction at $115,000 to $145,000 per self-serve bay and $250,000 per automatic bay (includes equipment). Tunnel car washes will vary from $500,000 to $2,000,000 for building and equipment depending upon construction style and length.
2. Check with the city to determine zoning requirements for the selected site.
3. Select an equipment supplier to help you through the design phase. Your supplier should be able to provide you with site analysis, financial forecasting, architect and general contractor recommendations, and city approval assistance.
4. Work with local architect/engineer and equipment supplier to discuss local building codes and necessary utility requirements.
5. Obtain a water, sewer, electric and gas availability letter from local utility authorities.
6. Architect/engineer draws complete set of building plans.
7. Submit plans to city for permitting and to potential contractors for construction bidding.
8. Finalize equipment order and select building contractor.
9. Obtain building permit and start construction.
10. Make application for utilities: gas, electric, water and sewer.
11. Complete construction and install car wash equipment.
12. Utilities turned on and car wash equipment started up.
13. Obtain occupancy permit and open your car wash for business!
TYPICAL CAR WASH COSTS
OTHER FACTORS TO CONSIDER